Our client, a long-time government contractor, rightly turned to Ifrah Law when it suspected a competitor had violated FAR regulations. Our client submitted a proposal in response to a government RFP to provide seminars and library services to detainees at the U.S. Naval Station Guantanamo Bay. The RFP stated that this would be a “lowest price technically available” (LPTA) contract.
Our client’s proposal was unsuccessful, and they moved to challenge the award. Our critical review of the record revealed that the successful bidder may have utilized unbalanced pricing. We successfully argued that our client’s pricing was balanced and potentially fairer to the government – a difficult argument to make in LPTA solicitations because of the discretion granted to contracting officers. Our challenge was successful and following the court’s order granting a preliminary injunction, the government was forced to take corrective action.
(Torres AES v. United States, 1:13-cv-00898 (Damich, J.))
IFRAH Law